The rodeo reconstruction project at Town Park moves into a new phase this week. Day parking at Town Park is impacted while construction crews work in the area.
Construction of the rodeo arena at Town Park started this week. As a result, the temporary day skier parking that was accommodated during the winter will return to active construction site. Parking & transportation information is available online at villageshuttle.com/
Construction on this project began after the final Snowmass Western Heritage Association's (SWHA) rodeo in 2023 and the anticipated completion date is early June, before the 2024 rodeo season.
The impacted area is shown in the solid red section in the image below.
Project information can be viewed online at: tosv.com/343/Town-Park-Planned-Updates