The Brush Creek culvert replacement project has begun. Periodic weekly updates will be provided throughout the project. Project information can be found online at tosv.com/566/Brush-Creek-Culvert-Reconstruction
Comments, feedback, or suggestions for improvement can be shared with project@tosv.com. We appreciate your patience during this construction project!
Closures:
- Brush Creek Road is now closed for the duration of the project.
What Work Was Completed This Week?
- Crews have completed the diversion of Brush Creek into a temporary pipe that will allow them to start the work underneath the old culvert pipe.
Work Planned for the Week of June 19:
- The sewer main extension will continue underneath Brush Creek.
Upcoming Traffic Flow Changes: