Snowmass Mall Transit Center
Last Content Update:
Share your thoughts on the Snowmass Mall Transit Center!
Submit your comments here.
Why Do We Need a New Transit Center?
World-class resorts require world-class transit services. The Village Shuttle and RFTA provide approximately 1 million rides each year through the Snowmass Mall and the capacities of both RFTA and Village Shuttle facilities are frequently reached during peak times.
What is the Current Status of the Transit Center?
Over the past 40 years, the Town has continually focused its efforts on finding the best solution for improving Transit access to and from the Snowmass Mall. In June of 2024, the Town Council gave staff the direction to pursue a plan for incremental improvements to the RFTA and Village Shuttle Depots. These improvements would include:
- Adding another bus bay to the existing RFTA Depot to better accommodate peak rider loading/offloading.
- Improving the West End of the mall by making it at-grade with the RFTA depot and thus providing safer and more ADA-compliant access to the mall.
- The addition of public restrooms to the RFTA Depot.
- Improving the Lot 6 crosswalk and staircase to create a safer and more intuitive pedestrian environment.
- The improvement and possible addition of elevators in the Village Shuttle depot for better connections to and from the Snowmass Mall level.
- A possible future phase could include further improvements to the Village Shuttle depot to accommodate more bus bays.
In March of 2024, the Town Council further directed staff to pursue the feasibility of a novel design for a combined Transit Center at the West End of the Mall. These designs are currently being reviewed by the Town Council.
-
Sam Guarino
Transportation DirectorPhone: 970-923-2543
-
Transportation
Physical Address
53A Elbert Lane
PO Box 5010
Snowmass Village, CO 81615
Phone: 970-923-2543Fax: 970-923-5986
New Snowmass Mall Transit Center
Building on the direction of Town Council, Town staff are developing a design for an improved transit experience at the terminus of the Snowmass Mall. This project engages transit partners, including Roaring Fork Transit Authority (RFTA), and the design firm, SEH. The design team was selected based on their expertise in transit facilities.
The design is currently underway, and input from the town, transit partners, and user groups is being incorporated.
February 18, 2025, Town Council Review
The Project Team presented the project to the Town Council on February 18, 2025. Materials from this meeting are available below:
- February 18, 2025, Transit Center Staff Report (PDF)
- February 18, 2025, Two-Level Design, No Garage (PDF)
- February 18, 2025, Two-Level Design, Parking Sketch (PDF)
- February 18, 2025, CDOT Email (PDF)
- February 18, 2025, 5-Year CIP, Transit (PDF)
- February 18, 2025, Public Comment, Transit Center (PDF)
February 3, 2025, Town Council Review
The Project Team presented the project to the Town Council on February 3, 2025. Materials from this meeting are available below:
- February 3, 2025, Transit Center Staff Report (PDF)
- February 3, 2025, Two-Level Design, No Garage (PDF)
- February 3, 2025, CIP Summary, Transit (PDF)
- February 3, 2025, Projected Revenues & Expenses 2024-2029 Report (PDF)
- February 3, 2025, FAB Recommendation, Transit Center (PDF)
- February 3, 2025, SGM Parking Lot Study (PDF)
- February 3, 2025, 2024 Incremental Improvements (PDF)
January 21, 2025, Town Council Review
The Project Team presented the project to the Town Council on January 21, 2025. Materials from this meeting are available below:
- January 21, 2025, Two-Level Mall Transit Station Design and Cost Estimation Staff Report (PDF)
- January 21, 2025, Two-Level Design (PDF)
- January 21, 2025, CIP Fund Overview (PDF)
- January 21, 2025, 27 Month Transit Center Cost Summary (PDF)
- January 21, 2025, 40 Month Transit Center Cost Summary (PDF)
- January 21, 2025, ROM Update (PDF)
January 13, 2025, Town Council Review
The Project Team presented the project to the Town Council on January 13, 2025. Materials from this meeting are available below:
- January 13, 2025, Mall Transit Center Staff Report (PDF)
- January 13, 2025, Mall Transit Center Draft Images (PDF)
- Planning Commission Resolution No. 2 - 2023 (PDF)
January 6, 2025, Town Council Review
The Project Team presented the project to the Town Council on January 6, 2025. Materials from this meeting are available below:
- January 6, 2025, Mall Transit Center Staff Report (PDF)
- 2024 Incremental Improvements (PDF)
- 2024 Two-Level Design (PDF)
- Lot 6 Transit Station Improvements (PDF)
- 2025 CIP Fund (PDF)
- January 6, 2025, 27 Month Transit Center Cost Summary (PDF)
- January 6, 2025, 40 Month Transit Center Cost Summary (PDF)
- Transit Center Design Competition (PDF)
Project Engagement
We want to hear from you! Your input is crucial in shaping the future of our transit center. Whether you're a regular commuter, resident, or just passing through, your feedback will help ensure that this project meets the needs of the community. Join us at public meetings, participate in surveys, or connect with us online to share your thoughts and ideas. Together, we can create a transit hub that is efficient, accessible, and welcoming for all.
Engagement Resources
- The public is invited to provide feedback on this project during the regular Town Council meeting on February 10. The meeting is being held in the Council Chambers at Town Hall (130 Kearns Road) at 4:00 p.m.
- Can’t make the meeting? Provide comments in other ways: tosv.com/544/Public-Comment-Participation-for-Public-